Projects for 2009-10
Funding of $500,000 through RARP and a one time contribution of $500,000 from the Infrastructure Stimulus Fund will cover the cost for the projects below.
| Dawson Gold Field Road | $220,000 | July-Sep. |
| Freegold Road | $200,000 | July-Sep. |
| South McQuesten Bridge | $150,000 | July-Sep. |
| Duncan Creek Road | $135,000 | Aug.-Oct. |
| South McQuesten Road | $100,000 | Aug.-Oct. |
| Nahanni Range Road | $100,000 | Aug.-Oct. |
| Casino Trail | $65,000 | July-Sep. |
| Davidson Creek Bridge | $30,000 | June-July |
Road Upgrade Work
|
![]() |
![]() |
Culvert & Bridge Work
|
Assistance Available
HPW provides assistance through planning, contracting and road upgrading work.
EMR liaises with industry and government in seeing projects through to their completion.
EcDev provides guidance undertaking economic impact assessments to ensure that projects provide a net economic benefit to Yukon.